Extension/Add on to an existing facility to allow for an additional 21 no. 4kW racks.

  • Obmg ltd works/input on the projectClient appointed consultant engineer to develop/prepare M&E design and build package, review and approve design by successful contractor, assist in IST development, commissioning witness testing, full snagging and final inspections..  In addition we were engaged by the successful contractor on the project to peer review the complete M&E design and build package as developed by their internal design engineering team.